30 Nov 2018

November 30 update

The construction of the new child care facility is 60% complete, with the installation of the structural steel, concrete slab pours and roof works. The builders have commenced installation of the internal partitioning framework, with fit-out works continuing through until Christmas.

Child Care Centre Keith Street project

The planned development of a new child care centre is part of the University’s commitment to supporting the career progression and development of staff and students with families.  There will be a fenced construction worksite (PDF, 772KB) established in the open grassed area situated north of P7, east of Keith Street, and west of Playing Field 8 to allow construction of a new 166-place child care and after school centre.

Affected areas

  • P7 parking – reduced parking bays northern end of P7
  • Open grassed area north of P7, east of Keith Street, and west of Playing Field 8

When

  • Start: Thursday 5 July 2018
  • Finish: Thursday 31 January 2019
  • Times: 7am to 4.30pm Monday to Friday; 7am to 1pm Saturdays

Contact

Steve Warfield, Construction Project Manager:

We apologise for the inconvenience this may cause and thank you for your patience during this time.