Physiology Refectory (63A) refurbishment update

8 May 2019

8 May update

Works are progressing well with the main base build nearing completion. All new tenant fit-out contractors have started their works onsite.

Work status:

  • roof and glazing completed
  • electrical and plumbing installations completed
  • air conditioning and extraction nearing completion
  • amenities completed
  • joinery and fixtures and fittings nearing completion
  • tenant fit-outs ongoing

The team appreciates your patience and assistance during these works.

Physiology Refectory construction May 2019
Physiology Refectory construction May 2019
Physiology Refectory construction May 2019
Physiology Refectory construction May 2019
Physiology Refectory construction May 2019
Physiology Refectory construction May 2019
Physiology Refectory construction May 2019
Physiology Refectory construction May 2019

 

Overall project

There will be construction work to refurbish the Physiology Refectory (63A). A new food complex to replace the existing Physiol refectory is due to open in semester one 2019. The centre will comprise seven food outlets, a self-service food preparation kitchen with microwaves, more indoor and outdoor seating, and improved access for people of all abilities. More information on the project is available on the project website.

Noisy work is scheduled to occur out of hours where possible to minimise disruption. Access through the construction zone will not be possible except in case of emergency. Please see this site map [PDF, 245KB]. Additional wayfinding signage will be installed.

Affected Areas

When

  • Start: Saturday 27 October 2018
  • Finish: Semester 1 2019

Contact

Brad Mortimer, Construction Project Manager

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

 