Priestley Building (67) and Building 69 refurbishment

9 Oct 2019

October update

Progress of refurbishment work of the Priestley Building (67) and Building 69  include:

  • Priestley Building (67)
    • Level 7 - pre-painting of walls
    • Level 6 - completion of wall sheeting, skirting duct installation, joinery site measures
    • Level 4 and 5 - completion of services rough-in in wall and sheeting of walls
    • External - removal of external window frames and ACM mastic, commencement of curtain wall south elevation and commencement of external window frame installation
  • Building 69
    • Level 8 –  installation of skirting duct, electrical fit-off, commencement of joinery and acoustic ceilings installation
    • Level 6 and 7 -  sheet and set walls, completion of services rough-in
    • External - completion of window installation on level 6, level 7 and level 8
Priestley Building refurbishment - August 2019
Priestley Building refurbishment - October 2019
Building 69 refurbishment - August 2019
Building 69 refurbishment, Level 7 - October 2019

Affected Areas

  • Priestley Building (67) level 2 foyer and levels 4 to 7
  • Building 69 level 6 to 8

When

  • Start: Monday 29 October 2018
  • Finish: Saturday 30 November 2019
  • Times: 6am to 4pm

Contact

Steve Warfield, Construction Project Manager

We apologise for the inconvenience this may cause and thank you for your understanding during this time.