There will be construction works occurring to the lifts in the Gehrmann Laboratories Building (60) to facilitate lift removal and upgrade.  

These works will cause limited lift usage, with only one lift being operational at any time until works are complete. Furthermore, the works may cause disruptions with movement around the building, and the occasional power shutdown.

Any noisy works and works that cause vibration will be undertaken early in the morning before 9am or after hours as agreed with stakeholders.

Affected areas

Lift 1 (level 1)

  • Start: 8 April 2019
  • Finish: 31 May 2019

Lift 2 (level 1)

  • Start: 6 September 2019
  • Finish: 17 October 2019
Gehrmann Laboratories lift plan
Gehrmann Lab lift works plan, level 1

Lift 80 (level 2)

  • Start: 20 August 2019
  • Finish: 30 September 2019