Please be advised a chiller is being installed on the roof of Ritchie Building (64A). These works will require the closure of Research Road and some minimal disruption to the Building 64 Block C lift.
The installation works will occur in stages across March.
Please see key dates below.
Preparatory Works
When
- Start: Tuesday, 2 March 2021 .
- Finish: Tuesday, 2 March 2021
- Times: 6am to 5pm
Crane Lift
When
- Start: Saturday, 6 March 2021
- Finish: Saturday, 6 March 2021
- Times: 6am to 12pm
Chiller Connection works
When
- Start: Saturday, 6 March 2021
- Finish: Wednesday, 17 March 2021
- Times: 6am to 6m
Affected Areas
- Research Road
- Ritchie Building 64A and Block C lift.
Work details
Closure of Research Road for crane lift onto the Building 64A roof. Access to roof required via Block C lift. Shutdowns may be required during this time
Project details
A chiller is being relocated from Gatton to be installed on the roof of Ritchie Building 64A [St Lucia] to ensure continuity of HVAC supply.
Contact
Casey Fredrickson, Project Manager (Infrastructure):
- Call: 0408 339 936
- Email: c.fredrickson@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.