Chiller Removed Gatton (8106)

26 Feb 2021

Please be advised a chiller is being removed from Building 8106 (John Mahon Stage II). These works will require the closure of the adjacent Animal Studies Carpark.

When

  • Start: Friday, 5 March 2021
  • Finish: Friday, 5 March 2021
  • Times: 6am to 10am

Affected Areas

  • Animal Studies Carpark.
  • Perimeter of Building 8106 (John Mahon Stage II).

Project details

A chiller is being relocated from Gatton to be installed on the roof of Ritchie Building 64A (St Lucia) to ensure continuity of HVAC supply.

Contact

Casey Fredrickson, Project Manager (Infrastructure):

We apologise for the inconvenience this may cause and thank you for your understanding during this time.