Power shutdown - 74 High St, Toowong

22 Mar 2021

NOTICE:

Generator Black Test

There will be a Power Shutdown at 74 High St, Toowong for black testing on the generators. 

Please see Black Testing Program here 

When

  • Start: Thursday, 15 April 2021
  • Finish: Thursday, 15 April 2021
  • Times: 5:30 – 6am

Affected Areas:

  • Building 490 - 74 High St, Toowong

Work Details

  • Isolate power to the building, there will be a momentary loss of power to all services for Approx. 30sec. Generator will start and run essential power services only. Generator runtime will be 30 min, Mains power will then be re-instated.

Contact

PF Assist

St Lucia Campus – Precinct 1: Rion Senior

St Lucia Campus – Precinct 2: Jeremy Moynihan

St Lucia Campus – Precinct 3: Craig Schaumburg

St Lucia Campus – Precinct 4: Robert Dore

Gatton: Scott Lennon

Remote Sites: Steve Lawler

UGL: James Tindall

We apologise for the inconvenience this may cause and thank you for your understanding during this time.