Please be advised a small landscaping project will be commencing shortly in the Chemistry forecourt to construct The Frank White Memorial Garden.
Site area mark up is attached for your reference. Footpath through access will be retained.
Affected Areas
- Chemistry forecourt
- Prentice (42)
- Liveris Building (46)
- Priestly Building (67)
- Chemistry Building (68)
When
- Start: Wednesday 1 September
- Finish: Wednesday 29 September
- Times: 6:30am - 5:00pm
Work details
- Landscaping works including earthworks, minor demolition, paving etc.
Contact
Jason Wright, Project Officer: P&F
- Call: 0432 753 920
- Email: jason.wright@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your patience during this time.
For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.