7 Sep 2021

Please be advised, there will be a power outage to the distribution board in Substation 24 for the installation of a power circuit.

Affected Areas

  • Duhig tower (2)
    • General Light and power in substation 24
    • Power to Comms Rack     

When

  • Start: Wednesday, 8 September 2021
  • Finish: Wednesday, 8 September 2021
  • Times: 6.00am to 6.30am

Work details

  • Install power circuit

Contact

Terence Cronk, Electrical Infrastructure Officer:

We apologise for the inconvenience this may cause and thank you for your patience during this time.