Construction Works at JD Story (61), level 4

28 Oct 2021

Please be advised, there will be works occuring in JD Story (61), Level 4, between 8 Nov and 6 Dec 2021 (22 working days).

Staff in offices affected by the works will be working in alternative locations between 8 Nov to 18 Nov 2021 whilst the AC is off.

Staff in offices on the other side of the corridor will not be affected and will continue to work in there.

Affected Area

When

  • Start: Monday 8 November 2021
  • Finish: Monday 6 December
  • Times: 7:00am to 4:00pm daily

Work details

  • Removal of AHU 4.1 so there will be no AC as highlighted on the attached PDF “Affected Area”
  • Brief power outages, if required, will be performed outside business hours 22 Nov and 23 Nov
  • Any noisy work will be done outside of business hours.

Project details

  • Temporary removal of two workstations ‘4’ & ‘5’
  • Removal of existing AHU 4.1
  • Removal of plant room wall
  • Replacement of new AHU 4.1
  • Construction of new plant room wall
  • Reinstallation of the two workstations.

Project Delivery Contact

Roger Goodwin , Transitions Project Manager:

We apologise for the inconvenience this may cause and thank you for your patience during this time.

For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.

Questions and feedback: