Lighting Retrofit at N.W. Britton Admin (8101)

19 Oct 2021

Please be advised, there will be lighting retrofit works will be conducted at Gatton Campus.

This will take place in N.W. Britton Administration (8101) & N.W. Britton Administration Annexe (8101A).

Affected Areas 

When

  • Start: Monday 25 October
  • Finish: Friday 26 November
  • When:  7:00am to 5:00pm

Work details

  • The work involves visiting every room where suitable fittings have been previously identified, installing LED fittings, and carrying out any maintenance required.
  • In some spaces, lights may be switched off at times during the day.
  • It is not feasible to give occupants an indication of the time when the electrician will turn up to each space. If the contractors turn up at an inconvenient moment, please advise them of a later time when they can return to complete the task.

Contact

We apologise for the inconvenience this may cause and thank you for your patience during this time.

For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.

Questions and feedback:

PF Assist
Property and Facilities

Latest