Power Outage to BWC (61A)

5 Oct 2021

Please be advised, there will be a power outage to the Level 5 Switchboard (61A) to install an Automatic Transfer Switch at the switchboard

Affected Areas

When

  • Start: Saturday, 9 October 2021
  • Finish: Saturday, 9 October 2021
  • Times: 6.30am to 2.00pm

Work details

  • Install an ATS to switchboard L 5

Project details

  • Essential Power Upgrade

Contact

Terence Cronk, Electrical Infrastructure Officer:

We apologise for the inconvenience this may cause and thank you for your patience during this time.

For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.