Asbestos works at Seddon (82)

26 Nov 2021

Please be advised, there will be extensive Asbestos Encapsulation and Hygiene work taking place at the Seddon Complex.

When

  • Start: Wednesday, 8 December 2021
  • Finish: Thursday, 9 December 2021
  • Times: 7:00am to 4:00pm

Affected Areas

  • Seddon Complex - Building 82A and 82B
    • the external roof walkway Level 5
    • Please see map attached

Work details

  • There will be an operational impact to Campus Operations staff and Contractors only
  • the access to this area would be restricted and all outdoor air conditioning units will not be accessible

Contact

Scott Lennon, P&F OHSW Manager:

Muhammad Sair, OHSW Adviser

We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.