Generator tests at Various UQ sites

12 Nov 2021

Please be advised, there will be generator testing at various sites which will cause a momentary loss to powerThese tests will be course of 11 months, therefore please read schedule for details.

When

  • Start: Thursday 25 November 2021
  • Finish: Monday 22 August 2021
  • When: 6:00am to 6:30am
  • Please see spreadsheet attached for specific dates and times of works 

Affected Areas

St Lucia

  • AIBN (75)
  • QBP (80)
  • Therapies Annex (84A)
  • QBI (79) 

Remote Sites

  • 74 High Street (490)
  • MBRS – Dunwich (site 26)
  • PACE (870)
  • Pinjarra Hills (401)
  • RBH- CCR (918)
  • Oral Health Centre (883) 

 Work Details

  • Isolate power to the building, there will be a momentary loss of power to all services for Approx. 30sec.
  • Generator will start and run essential power services only. Generator runtime will be 30 min, Mains power will then be re-instated.

 Program Change

  • Any requests to change the attached program are to be communicated to the UGL staff below in writing prior to the date of testing.
  • Acceptance of any changes will be supported by confirmation in writing from UGL staff once changes have been implemented.  
  • Any changes to the program that cause UQ assets to be outside of their scheduled compliance testing will require prior approval from Andy Sumner.

Contact

PF Assist

Maintenance Contract Manager – Andrew Sumner

UGL: Brody Lucas / James Tindall

St Lucia Campus – Precinct 1: Rion Senior

St Lucia Campus – Precinct 2: Jeremy Moynihan

St Lucia Campus – Precinct 3: Scott Newton  

St Lucia Campus – Precinct 4: Robert Dore

Gatton: Taylor Jeffreys

Remote Sites: Steve Lawler