Demolition works will commence for the Plant Grow Facility on the project site located at the corner of Glasshouse Rd and Services Road. Site establishment and preparation works will commence from the 6th of December 2021.
Affected Areas
- Building 87
- Storage Facility (85A)
- Growth Room (89D)
- Glasshouse Building (88)
When:
- Start: Monday 6 December
- Finish: Friday 17 December
Work details
- 6/12/2021 to 7/12/2021 – Commence disassembly of B87 temporary office
- 8/12/2021 – Mobile crane on site to remove B87 temporary office
- 9/12/2021 – Installation of construction site fencing
- 13/12/2021 to 17/12/2021 – Demolition of existing buildings (B85A, B89D, B88)
Project details
- The Plant Growth Facility (PGF) project will provide world-leading research facility that will contain an array of highly technical controlled environment rooms, capable of replicating a variety of environmental conditions to simulate natural conditions in a controlled and measurable manner.
- The facility will also include a glasshouse on the roof deck for further plant science research capability.
Summary Project Program
- Start: Monday, 29 November 2021
- Finish: Monday, 10 July 2023
- when: 7:00am to 5:00pm
Contact
Emmanuel Vasiliou, P&F Project Manager:
- Call: +61 408 172 187
- Email: e.vasiliou@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page