Road resurfacing works on Cooper Road & research Road

17 Dec 2021

Please be advised, there will be road resurfacing works on sections of Cooper Road and Research Road. These works will be staged to enable as much access as possible for the duration of the project (refer attached staging plan)The project will endeavour to undertake noisy works in the morning before work hours.However, it is advised that where possible occupants make arrangements to work from home to limit disruption.  

When

  • Start: Monday 10 January 2022
  • Finish: Wednesday 9 February 2022
  • Times: 6:00am – 5:00pm
    • Stage 1: 10/1/21 to 24/1/21 (15 days)
    • Stage 2: 25/1/21 to 6/2/21 (13 days)
    • Stage 3a & 3b: 7/2/21 to 9/2/21 (3 days)

Affected Areas

  • Cooper Rd
  • Research Rd
  • QBI (79)
  • Cumbrae-Stewart (72)
  • Gehrmann (60)
  • Ritchie (64A)
  • Chemistry (68)
  • Hawken (50)
  • Molecular Biosciences (76)
  • Yumantra

Work details

  • Removal of temporary patching in road.
  • Concrete cutting.
  • Reinstatement of new concrete (including sufficient time for curing).

Contact

Jason Wright, Project Officer: P&F

We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.

Questions and feedback:

PF Assist
Property and Facilities