Please be advised, there will be crane works at the roof of the Queensland Bioscience Precinct (80) to repair damage to the Glasshouse buildings.
Affected Areas
- Chancellors Place
- Queensland Bioscience Precinct (80) roof
- Glasshouse Buildings (88/89)
When
- Start: Saturday, 29 January 2022
- Finish: Wednesday, 2 February 2022
- Times:
- Saturday - 6:00am to 9:00am
- Monday to Wednesday – 7:00am to 4:00pm
Work details
- a mobile crane lifting sheeting and edge protection scaffolding onto the roof of Building 80 from Chancellors Place to repair damage to the Glasshouse buildings.
- Saturday 29January – Crane set up to lift materials onto the roof of Building 80 prior to carrying out repair works the following week. See attached plan for crane setup location.
- Monday 31 & Tuesday 1 February - Set up edge protection scaffold along the edge of the Glass houses.
- Wednesday 2 February - Scissor lift and equipment delivery and works to start on replacement of roof sheeting.
Contact
Alan Deuchars, Arc. Commercial Project Manager:
- Call: 0429 961 380
- Email: alan.deuchars@arcprojects.com.au
We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.