Please be advised there will be ongoing works as both the Industrial Centre (85) and the P&F Gardeners Compound are being developed. This is to allow for the development of the new Multifunctional Green Space including Landscaping and Garden Seating.
Affected Areas
- Old Gardeners Compound adjacent Campus Lodge & International House
- Industrial Centre (85)
- Otto Hirschfield (81)
- Seddon (81)
- Therapies Building (84)
- Building (87)
- Building (96)
- Building (97)
- International House (36A)
- Cromwell College (36B)
When
- Start: Tuesday, 26 April 2022
- Finish: Friday, 29 April 2022
- Times: 7:00am to 5:00pm, Monday to Saturdays, though works may finish earlier.
Work details
Gardeners Compound
- Small excavator and bobcat works. Noise will be kept to a minimum.
- External concrete works to pathway, ramps and garden pavement area (crazy pave)
- Commencement of DDA compliant kerb, channel and footpath works on Services Road.
- Excavation for installation of electrical services.
- Form, reinforcement and pour in-situ concrete furniture
Project details
- The old Fleet Compound will be replaced with an open landscaping area for UQ’s wider Multifunctional Green Space Project