There will be a road and footpath closure on Old Cooper Rd due to a crane establishment to remove the site sheds from Level 6 of AIBN.

Affected Areas

When

  • Start: Thursday, 5 May 2022
  • Finish: Thursday, 5 May 2022
  • Times: 6:00am to 2:00pm

Work details

Schedule as per below

  1. Establish exclusion zone for Old Cooper Rd at 6am
  2. Crane establish on site from 6am
  3. Remove site sheds from Level 6
  4. Crane demobilise approximately 12pm to 2pm.

Important Information

  • Pedestrian access on Old Cooper Rd will be restricted during the crane lifting activities.
  • While the crane is not operational, access will be controlled by the traffic controllers on site.

Contact

Emmanuel Vasiliou, UQ Project Manager:

We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.