Construction works will commence in AIBN (75), level 2 for the NCRIS Facility ANFF-Q Clean Room Project.
Affected Areas
- Level 2, Australian Institute for Bioengineering and Nanotechnology - AIBN (75)
- Please see attached map of works
When
- Start: Monday, 6 June 2022
- Finish: Friday, 9 September 2022
- Times: 6:30am to 6pm
Upcoming Work details
- 6th June 2022 to 7th June 2022
- Site establishment and installation of hoardings
- 8th June 2022 to 17th June 2022
- Demolition
Project details
The project involves:
- The removal of the existing Interaction, Meeting Room, Kitchen and Child Friendly Workspace
- Construction of a new Class 10,000 Clean Room extension with adjacent Kitchenette, Child Friendly Workspace, localised Plant room and upgraded services and reticulation to Plant Room 1.
- Refurbishment of the existing Class 10,000 Clean Room and Class 1,000 Clean Room to upgrade facilities.
Contact
Kevin Park, Project Manager:
- Call: +61 400 009 276
- Email: k.park1@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.