Please be advised, there will be 6 monthly UPS testing to Precinct 1 and 2 at St Lucia Campus as per preventative maintenance program attached.
When
- Start: Tuesday 17 May 2022
- Finish: Thursday 9 June 2022
- Times: 6:00am to 3:30pm
Where
- Precinct 3
- Please see program attached for more information
Work details
- UPS static bypass operation check.
- External bypass operation check. (Where exists)
- UPS on-load test as follows. (With load connected to UPS)
- Monitor battery string voltage, if okay continue otherwise check individual cells to determine faulty unit.
- Isolate mains.
- Monitor battery string voltage and record voltage and time.
- Cease test immediately if battery failure detected, otherwise continue to test until battery voltage is at 105% of UPS manufacturers low voltage threshold.
- For multi battery string UPS’s: -
- Isolate one string at a time.
- Measure individual cell voltages.
- Remove external load.
- Measure individual cell voltages.
Contact
James Tindall
- Call: 0423 404 036
- Email: James.tindall@ugllimited.com
Luke Cahill
- Call: 0412 580 078
- Email: Luke.cahill@ugllimited.com
We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.