Please be advised, there will be an isolation of mechanical services to Glasshouse 5 in building 89E to restore air conditioning operation of the glasshouse.
Affected Areas
- All glass house compartments for glasshouse 5
When
- Start: Thursday, 9 June 2022
- Finish: Thursday, 9 June 2022
- Times: 6:00am to 10:00am
Work details
- The chiller and HVAC plant will be shut down so that power can be connected to a new Controls Panel.
Project details
- This is part of a project to restore full control and monitoring of the air conditioning systems for Glasshouse 5.
Contact
Neil Brown, Senior Building Systems Engineer:
- Call: 07 3346 1270
- Email: n.brown@pf.uq.edu.au
We apologise for the inconvenience this may cause and thank you for your patience during this time. For more information on campus shutdowns, disruptions and road closures please refer to the Property and Facilities Division Road and buildings works page.