Ongoing Works Disruptions: UQ Centre for Clinical Research (918)

27 Sep 2022

There will be disruption to the UQ Centre for Clinical Research (918) as part of the façade replacement project. Please see information below on works planned for the next few weeks.

The UQ CCR façade replacement project is expected to be completed in August 2023.

Permanent Disruptions
  • RBWH Parking Bays 17 – 23: These parking bays will be closed to enable suitable road width for passing vehicles, safe use of the area and will be used for construction storage.
  • Myrtle Lane: The lane width will narrow, and a give way arrangement will be in place with traffic control in place during the day. Occupants should expect some delays to deliveries into the UQ CCR loading dock.
  • UQ CCR & Pulse Café Bin Storage Area: Bin storage will be relocated to the loading dock.
  • Pedestrian Gantry in Zones 1 & 2 will be in place until the close of the works

The above arrangements are expected to be in place until approx. May 2023.

Ongoing Works Disruptions

Please refer to the UQ CCR Zone image below for more information.

When
  • Start: Saturday, 24 September 2022
  • Finish: Sunday, 9 October 2022
  • Times: 6:30am – 6:00pm
24/09/2022 – 02/10/2022

Impacted Area

Disruption

Date & Time

Zone 1 & 2

  • Complete mast climber sign-off & commence operation
  • Removal of existing panels via rope access

 

Ongoing

6:30am – 6:00pm

Zone 3

No works during this period

Zone 4

  • Scaffold install up to level 06 and 07
  • Ongoing demolition of panels to lower levels. There will be intermittent noise with these works.

Ongoing

6:30am – 6:00pm

  • Myrtle Lane closure for deliveries.
  • Access to Myrtle Lane from Central Drive will reopen by 7:00am.

27/09

4:00am – 7:00am

  • Access to northern most offices between Levels 03 and Levels 08 to undertake mould inspections

29/09

All Day

Zone 5

No works during this period

 

Zone 6

No works during this period

 

03/10/2022 – 09/10/2022

Impacted Area

Disruption

Date & Time

Zone 1 & 2

  • Mast climber in operation to commence panel removal
  • Removal of existing panels via rope access

Ongoing

6:30am – 6:00pm

Zone 3

No works during this period

 

Zone 4

  • Continue scaffold installation.
  • Ongoing demolition of panels to lower levels. There will be intermittent noise with these works.

Ongoing

6:30am – 6:00pm

Zone 5

No works during this period

 

Zone 6

No works during this period

 

Project details

These works are part of the Herston Package Façade replacement project. For more information on the Façade Replacement Program, please visit the website.

Contact

Casey Fredrickson, Associate Director, Infrastructure Projects:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.