There will be an isolation to all amenities to the Rugby Club (29A) to allow installation of 150mm concrete base in sewer pit.
Affected Areas
- Amenities at the UQ Rugby Club (29A)
When
- Start: Monday, 26 September 2022
- Finish: Tuesday, 27 September 2022
- Times: 6:30am to 3:00pm
Work details
Quoted works: sewer pit reform.
Project details
- Fill out all confined space and isolation permits.
- Plug all inlets to pit and isolate power to pumps.
- Suck out sewer pit and remove pumps.
- Remove guide rails and duct foot.
- High pressure clean sewer pit.
- Set up tripod and test atmosphere for gases.
- Install reinforcing mesh on floor of sewer pit.
- Pour 150mm thick slab in sewer pit with fast cure concrete.
- Install guide rails and duct foot in pit.
- Use crane to install pumps.
- Fill pit and set floats.
- Test pumps and clean site.