Pluming Works: Rugby Club (29A)

23 Sep 2022

There will be an isolation to all amenities to the Rugby Club (29A) to allow installation of 150mm concrete base in sewer pit.

Affected Areas
When
  • Start: Monday, 26 September 2022
  • Finish: Tuesday, 27 September 2022
  • Times: 6:30am to 3:00pm
Work details

Quoted works: sewer pit reform.

Project details
  • Fill out all confined space and isolation permits.
  • Plug all inlets to pit and isolate power to pumps.
  • Suck out sewer pit and remove pumps.
  • Remove guide rails and duct foot.
  • High pressure clean sewer pit.
  • Set up tripod and test atmosphere for gases.
  • Install reinforcing mesh on floor of sewer pit.
  • Pour 150mm thick slab in sewer pit with fast cure concrete.
  • Install guide rails and duct foot in pit.
  • Use crane to install pumps.
  • Fill pit and set floats.
  • Test pumps and clean site.
Contact

Kevin Steytler, Axis Manager :

We apologise for the inconvenience this may cause and thank you for your understanding during this time.