There will be contaminated soil removed (from site) at the Industrial Centre (85) to allow for development of Green Space including landscaping and garden seating. Traffic control will be set up on Hood Street.
There will be 6 in number truck movements daily over the 2-day course of the works (Please refer to the traffic plan attached).
Affected Areas
- Industrial Centre (85)
- Otto Hirschfield (81)
- Curtis (82l)
- Seddon (82)
- Therapies Building (84)
- Building (87)
- Building (96)
- Building (97)
- International House (36a)
- Cromwell College (36b)
When
- Start: Wednesday, 28 September 2022
- Finish: Thursday, 29 September 2022
- Times: 7:00am to 5:00pm
Work details
Delivery of excavator (approx. 7:30am Wed 28 September 2022)
Excavation works to remove approx. 250 cubic metres of contaminated soil both days.
There will be 6 semi-trailer loads removed per day over the scheduled 2 days.
Project details
Removal of contaminated soil and develop the site as Green Space
Contact
Steve Warfield, Senior Project Manager:
- Call: 0428 051 360
- Email: s.warfield@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.