Please be advised that works are scheduled at Foxtail (1019) to install new chilled water valves as part of the Foxtail Materials Characterisation project for the 26th of October.
For the duration of these works, there will be disruptions to air-conditioning services in the building.
Affected area
When
- Start: Wednesday, 26 October 2022
- Finish: Wednesday, 26 October 2022
- Times: 6:00 am to 8:30 am (times are approximate)
Work details
The building’s chilled water system will be offline for approximately 2 hours to enable the installation of new tees and valves for the new level 2 mechanical system.
To avoid disruption to the building occupants, the contractor will undertake these works between 6:00 am and 8:30 am.
Project details
Chilled water valve cut-in as part of the Materials Characterisation project.
Contact
Kevin Park, Project Manager:
- Call: +61 400 009 276
- Email: k.park1@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.