There will be some disruption to the Duhig North (12) and surrounding areas due to the façade replacement works.
Further disruptions will continue to be communicated.
This project is due for completion in January 2023.
Please find attached the map to the disruptions. (JPG, 201.8 KB)
Affected Area & Disruption | Time | Date |
Duhig North (east) - Above café Boom Lift required to access high-level eaves.
| 6:00am – 5:00pm | 26th September 2022 to 24th October 2022 |
Duhig North (west) - University Drive Eave Demolition and installation
| 6:00am – 5:00pm | 21st September to 27th October |
Duhig North (north) - Duhig Laneway Eave Demolition and installation
| 6:00am – 5:00pm | 21st September to Mid-November [Note: Sir Llew Edwards cladding replacement in this Laneway will follow] |
Duhig North (south) Scaffold installation & boom lift
| 6:00am – 5:00pm | 20th October to Mid-November |
Project details
Duhig North Building façade replacement project.
Contact
Casey Fredrickson, Project Manager (Infrastructure):
- Call: 0408 339 936
- Email: c.fredrickson@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.