Façade Project: Sir Llew Edwards (14)

12 Oct 2022

There will be some disruption to Sir Llew Edwards (14) and surrounding areas due the façade replacement project.

Further disruptions will continue to be communicated.

Expected completion date for the project is January 2023.

Affected areas

When

  • Start: Monday 10 October
  • Finish: Saturday 5 November
  • Times: 6:00am to 5:00pm

Affected Area & Disruption

Time

Date

Atrium

  • Rectification of lawn and pathways following removal of scaffold

For duration

10th October to 17th October

Campbell Road Elevation

Installation of Cladding to fins and eaves

  • Noisy works
  • Footpath & road exclusion zones
  • Minor noise (beeping from Boom lift)

6:00am – 5:00pm

29th August 2022 to Md-November

Duhig Lane

Demolition of panels on Duhig North Building

  • Noisy works
  • Exclusion zones within laneway (entry/exit via hoarding)

6:00am – 5:00pm

Mid-August to Mid-November 

Terrace Room Balcony –

Exclusion zone required for cladding works –

  • Noisy works due to installation of cladding

For duration

Full balcony closure

August 2022 to 29th October 2022

Project details

Sir Llew Edwards building façade replacement project.

Contact

Casey Fredrickson, Project Manager (Infrastructure):

We apologise for the inconvenience this may cause and thank you for your understanding during this time.