Façade Replacement Works: UQCCR (Building 918)

10 Oct 2022

There will be disruption to the UQ Centre for Clinical Research (Building 918) as part of the façade replacement project.

Please see information below on works planned for the next few weeks.

The UQ CCR façade replacement project is expected to be complete in August 2023.

Permanent Disruptions

  • RBWH Parking Bays 17 – 23. These parking bays will be closed to enable suitable road width for passing vehicles, safe use of the area and will be used for construction storage.
  • Myrtle Lane: The lane width will narrow, and a give way arrangement will be in place with traffic control in place during the day. Occupants should expect some delays to deliveries into the UQ CCR loading dock.
  • UQCCR & Pulse Café Bin Storage Area: Bin storage will be relocated to the loading dock.
  • Pedestrian Gantry in Zones 1 & 2 will be in place until the close of the works.

The above arrangements are expected to be in place until approx. May 2023.

Ongoing Works Disruptions:

  • Refer to the UQCCR zone mark-up map below for more information.
  • Dates: Monday 10 October 2022 – Sunday 23 October 2022
  • Times: 6:30am – 6:00pm

10/10/2022 – 16/10/2022

Impacted Area

Disruption

Date & Time

Zone 1 & 2

  • Mast climber in operation for panel removal
  • Water testing to northern and southern window coves

Ongoing

6:30am – 6:00pm

Zone 3

No works during this period

Zone 4

  • Scaffold install up to level 07 & 08
  • Ongoing demolition of panels to lower levels.
  • There will be intermittent noise with these works.

Ongoing

6:30am – 6:00pm

  • Myrtle Lane closed for deliveries on the 11th & 13th of October.
  • Access to Myrtle Lane from Central Drive will reopen by 7:00am.

11/10/22 & 13/10/22

4:00am – 7:00am

Zone 5

  • Removal of existing façade

Ongoing

6:30am – 6:00pm

Zone 6

No works during this period

 

17/10/2022 – 23/10/2022

Impacted Area

Disruption

Date & Time

Zone 1 & 2

  • Mast climber in operation for panel removal
  • Removal of existing panels via rope access

Ongoing

6:30am – 6:00pm

Zone 3

No works during this period

 

Zone 4

  • Continue scaffold installation.
  • Ongoing demolition of panels to lower levels.
  • There will be intermittent noise with these works.

Ongoing

6:30am – 6:00pm

  • Myrtle Lane closed for deliveries on the 18th of October.
  • Access to Myrtle Lane from Central Drive will reopen by 7:00am.

 

18/10/22

4:00am – 7:00am

Zone 5

  • Removal of existing façade

Ongoing

6:30am – 6:00pm

Zone 6

No works during this period

 

24/10/2022 – 30/10/2022

Impacted Area

Disruption

Date & Time

Zone 1 & 2

  • Mast climber in operation for panel removal
  • Removal of existing panels via rope access

Ongoing

6:30am – 6:00pm

Zone 3

No works during this period

 

Zone 4

  • Continue scaffold installation.
  • Ongoing demolition of panels to lower levels.
  • There will be intermittent noise with these works.

Ongoing

6:30am – 6:00pm

  • Myrtle Lane closed for deliveries on the 24th of October.
  • Access to Myrtle Lane from Central Drive will reopen by 7:00am.

 

24/10/22

4:00am – 7:00am

Zone 4

  • Continue scaffold installation.
  • Ongoing demolition of panels to lower levels. There will be intermittent noise with these works.

Ongoing

6:30am – 6:00pm

Zone 5

  • Removal of existing façade

Ongoing

6:30am – 6:00pm

Zone 6

No works during this period

 

Project details

These works are part of the Herston Package façade replacement project.

For more information on the Façade Replacement Program, please visit the website.

Contact

Casey Fredrickson, Associate Director, Infrastructure Projects:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.