Power Shutdown: QBP (80)

10 Oct 2022

There will be a shutdown to QBP (80), level 3, 5 & 7 to install/maintain a variety of electrical works. Please find attached plans below for detailed areas.

Affected areas

When

  • Start: Tuesday, 11 October 2022
  • Finish: Tuesday, 11 October 2022
  • Times: 6:00am to 8:00am

Work details

  • DB 5CN to install 1x RCBO for outstanding works (Level 5)
  • DB 3GE to disconnect 1x circuit breaker (Level 3)
  • DB 7CE to install 1x circuit breaker (Level 7)

Contacts

James Tindall (UGL):

Luke Cahill (UGL):