Please be advised there will isolation of water to Elkhorn (1024) to allow the installation of a reduced pressure zone device (RPZD).
Affected areas
- Elkhorn (1024) – whole of building
When
- Start: Saturday 15 October
- Finish: Saturday 15 October
- Times: 6:30am to 3:00pm
Work details
These are quoted works and will involve:
- Isolation of water to the building
- Supply and installation of an 80mm RPZD with butterfly valves and strainer on bypass watermain
- Reparing of all non-compliant works.
Contact
Kevin Steyler, Axis Manager:
- Call: +61 411 303 649
- Email: kevin@axisms.com.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.