There will be an isolation of water to Michie (9) for the installation of pressure regulating valves (PRV’s) as part of quoted works.
Affected areas
- Michie (9) (whole of building)
When
- Start: Saturday, 22 October 2022
- Finish: Saturday, 22 October 2022
- Times: 5:00am to 3:00pm
Work details
The works will involve the following actions:
- Isolation of water on each level
- Installation of PRV’s to each level
- Setting PRV’s to 500kpa and testing pressures
- Checking for leaks and cleaning up area
Contact
Dean Rogers (Axisms), Plumber:
- Call: +61 420 941 379
- Email: dean.rogers@axisms.com.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.