17 Nov 2022

Please be advised room 122 will be closed in AEB (49), level 1 to allow for the installation of submains onto the cable tray.

Affected areas

When

  • Start: Wednesday, 23 November 2022
  • Finish: Wednesday, 23 November 2022
  • Times: 6:00am to 3:00pm

Work details

Full access would be required to this room for the duration of the day. Please make adjustments to room bookings if you require room 122.

Electricians will be installing large submains through this room and will require space to complete this work safely.

Project details

This work is to allow the reticulation of submains from AEB to Zelman Cowen.

Contact

James Dwyer, SEIE:

Bryson Lunam, Electrical contractor:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.