Please be advised there will be a footpath closure running on Sir Fred Schonell Drive in front of Car parks P3 (98b) and P4 (98a). The footpath is being replaced as well as the Irrigation mainline.
Affected areas
- Footpath from pedestrian crossing on Sir Fred Schonell Drive to exit lane of P3 and P4 carparks
- Please find attached pathway closures for work hours (PDF, 760.1 KB), and pathway closures for after hours. (PDF, 285 KB)
When
Demolition removal of path, installation of irrigation main line.
- Start Wednesday, 30 November 2022
- Finish: Tuesday 6 December 2022
- Times: 7:00am to 4:00pm.
Concrete pour of new pathway
- Start Tuesday, 6 December 2022
- Finish: Friday, 9 December 2022
- Times: 7:00am to 4:00pm.
Work details
There will be a footpath closure for the installation of new foot path.
Contact
Shane Biddle, Manage (Grounds):
- Call: 0411020471
- Email: s.biddle@pf.uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.