Please be advised, there will be a road closure to Jocks Road between Zelman Cowen (51) and AEB (49) to allow for the installation of electrical mains under Jocks Road.
Affected areas
- Jocks Road
- Zelman Cowen (51)
- AEB (49)
When
- Start: Saturday, 19 November 2022
- Finish: Saturday, 19 November 2022
- Times: 6:00am to 12:00pm
Work details
The works will prohibit any vehicle access to the Lakes/Amphitheatre site gate at the end of Jocks Road.
Some minor pedestrian access may be permitted at certain times, all foot traffic should be advised to find an alternate route.
Project details
This road closure is to allow for the safe installation of electrical sub mains between Zelman Cowen and AEB.
Contact
James Dwyer, SEIE:
- Call: 0457036107
- Email: james.dwyer@uq.edu.au
Bryson Lunam, Electrical contractor:
- Call: 0449577528
- Email: bryson@npcontracting.com.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.