Please be advised there will be disruptions to the air conditioning to AIBN (75) and Steele (3) to allow Fire/HVAC interface testing.
Affected areas
When
- Start: Wednesday, 21 December 2022
- Finish: Wednesday, 21 December 2022
- Times: 6:00am to 2:00pm
Work details
The design of the air condition system is to stop during a fire alarm while it is active on a floor. When the fire alarm is not active on the floor the AC will continue to run.
Test time should be off no longer than 1 hour per test with a 15 min on period between tests.
With the milder condition expected, the impact will be minimal.
The system will return to normal after testing.
Contact
Dale Coulson, Service Technical:
- Call: 0456414605
- Email: dcoulson@agcoombs.com.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.