Please be advised there will be disruptions to the air conditioning to QBP (80) for Fire/HVAC interface testing.
Affected areas
- Queensland Bioscience Precinct, QBP (80), whole building
When
- Start: Thursday, 29 December 2022
- Finish: Friday, 30 December 2022
- Times: 6:00am to 2:00pm
Work details
The design of the air condition system is to stop during a fire alarm is active on a floor. When the fire alarm is not active on the floor the AC will continue to run.
Test time should be off no longer than 1 hour per test with a 15 min on period between tests.
With the milder condition expected, the impact will be minimal.
The system will return to normal after testing.
Contact
Dale Coulson, Service Technician:
- Call: 0456414605
- Email: dcoulson@agcoombs.com.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.