Please be advised there will be disruptions to the air conditioning in AIBN (75) to the whole building to allow for Fire/HVAC interface testing
Affected areas
When
- Start: Wednesday 18 January 2023
- Finish: Wednesday 18 January 2023
- Times: 6:00am to 2:00pm
Work details
The design of the air condition system is to stop during a fire alarm while it is active on a floor. When the fire alarm is not active on the floor the AC will continue to run.
Test time should be off no longer than 1 hour per test with a 15 min on period between tests.
With the milder condition expected, the impact will be minimal.
The system will return to normal after testing.
Contact
Dale Coulson, Service Technician:
- Call: 0456414605
- Email: dcoulson@agcoombs.com.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.