Footpath Works: Corner of Services Rd & Hood Street, St Lucia

18 Apr 2023

Please be advised there will be builders footpath works occurring at the corner of Services Road & Hood Street, St Lucia Campus, plan of site works attached (PDF, 164.9 KB)

These works will restrict access to the footpath directly adjacent the old Fleet Compound. Works are required to allow for replacement of the old footpath.

Affected areas

  • Access to footpath adjacent Old Fleet Compound building at corner of lower Hood Street and Services Road

When

  • Start: Tuesday, 18 April 2023
  • Finish: Monday, 24 April 2023
  • Times: 6:00am to 6:00pm

Work details

There will be full safe traffic management in place for both pedestrian and vehicle movements.

Date

Works

Tuesday 18th April 2023

  • Saw cut existing footpath
  • Demolition of existing kerb and channel
  • Demolition of Footpath

Wednesday 19th April 2023

  • Form and pour new kerb and channel

Thursday 20th April 2023

  • Form and pour new kerb and channel
  • Form and pour new footpath

Friday 21st April 2023

  • Form and pour new Footpath

Saturday 22nd April 2023

                                                          

  • Form and pour new Footpath

Monday 24th April 2023

  • Form and pour new Footpath

Project details

Printery Gardens Project

Contact

Steve Warfield, Senior Project Manager:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.