Repair of Concrete Awnings: Zelman Cowen (51)

26 Jul 2023

Due to the inclement weather in June, please find below our updated timeframe and program for Zelman Cowen (51).

There will be continued disruptions to Zelman Cowen (51) for the repairs of the concrete awnings on level 2,3 and 4

Stage 1 has been completed and we are in progress for Stage 2.

Stage 1 (COMPLETED) in Red is proposed to commence from the 19thJune – 14th July 2023

  • Noisy works will commence from 6:30 am and cease at 9:00am.
  • 9:00am – 4:00pm will be quiet. Work will be patching and light hand tools

Stage 2 (amended) in Green is proposed to commence from the 17th of July – 31st August 2023

  • Noisy works will commence from 5:30am and cease at 8:00am.
  • 8:00am – 4:00pm will be quiet.
  • Work will be patching and light hand tools

Access

  • Spotters will be onsite for the duration of the works and alternate routes will be in place. Where works occur over entry ways these works will be mainly completed during the noisy work times. This will minimise closures.
  • All emergency egress will be maintained for the duration of the works.
  • Only one entry will be affected at a time.
  • PWD access will be maintained at all times and in the event of any persons that require access, all works will cease to allow access at any time for person requiring disability access.

Works Duration

  • Start: Monday, 19 June 2023
  • Finish: Monday, 31 August 2023

Project details

Repair of concrete awnings

Contact

Stephen Ingham

We apologise for the inconvenience this may cause and thank you for your understanding during this time.