Please be advised there will be disruptions at Ritchie Research Laboratories (64A) to undertake cladding investigation works. There will be intermittent noise throughout the duration of the investigations.
Project Duration
- Date: Friday 14 April 2023
- Duration: 6:30am – 12:00pm
Affected Areas
External service balconies
- The contractor will be completing an inspection of the services.
Level 1B
- The contractor will be accessing the external panelling to level 1B. There will be intermittent noise throughout the duration of the investigations.
Work details
This project involves completing investigations to the existing cladding panels via ground to level 1B and a services inspection via the services balconies.
More information on the Façade Replacement program of works can be found here: https://coo.uq.edu.au/operational-areas/property-and-facilities/pf-projects-and-initiatives/facade-replacement-project
Contact
Tegwen Butler, Project Manager (Infrastructure):
- Call: 0406 335 583
- Email: tegwen.hunter@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.