There will be a road closure next to the Multifaith Chaplaincy (38) to allow unloading and installation of new gym equipment.
The road closure will take place from approximately 6:00am to 9:00am, with the entire installation job finishing at 5:00pm.
Affected areas
- Multifaith Chaplaincy (38), disabled parking bay
- McElwain (24A), level 2 entry
- Social Sciences (24), level 2 entry
- Building 31A level 1 south access
When
- Start: Thursday, 13 April 2023
- Finish: Thursday, 13 April 2023
- Times: 6:00am to 5:00pm
Work details
Phase 1 truck parking to unload (road closure 6:00am to 9:00am)
- Technogym arrival and parking of truck at the top of the road.
- Barriers to be positioned around impacted areas.
- Complete safety walk through venue to locate equipment being removed.
- Unloading and unboxing equipment at the rear of the truck.
- Packaging to remain with the truck.
Phase 2 truck parking on completion of unload and re-opening of road (9:00am until 5:00pm or completion of installation)
- Remove barriers from truck area
- Move truck to space identified adjacent to building 31b
- Complete installation
Contact
Ben Fisher, Operations Manager UQ Sport
- Call: +61 417 669 155
- Email: bfisher@uqsport.com.au