There will be some disruption at Sir Llew Edwards building as per the Figure 1 mark-up below in relation to the cladding replacement project works.

Following a final inspection, a couple of minor defects have been identified which require rectification.

Affected areas

  • Duhig Laneway vehicular access
  • Level 6 Balconies, including Terrace Room Balcony
  • Exclusion zones at the corner of University Drive and Campbell Rd
  • Exclusion zones adjacent to Sir Llew Edwards building entrance
  • Footpath closure in June for pavement replacement works

When

 Facade and Footpath Rectification

  • Start: Monday, 3 July 2023
  • Finish: Thursday 6 July 2023
  • Times: 6:00am to 5:00pm

Work details

The Contractor will be returning to site to complete some defect rectification works for the Sir Llew Edwards Facade Replacement works.
This will involve disruption to footpaths and Duhig Laneway, as per the Figure 1 mark-up below.

These works will create some noise due to machinery beeping as well as some minor noise expected from cladding rectification.

A section of footpath adjacent to the Campbell Rd building front entrance will be closed for a period of time between the3rd and 5th July to replace the cracked footpath.
This will involve concrete cutting and vac truck on site which is expected to create some noise.

Figure 1 – Works Impacts

Project details

Sir Llew Edwards Façade Replacement Project

Contact

Casey Fredrickson, Senior Project Manager (Infrastructure):

We apologise for the inconvenience this may cause and thank you for your understanding during this time.