Fire/HVAC Testing: Various Buildings

8 May 2023

Please be advised there will be a disruption to the air conditioning to the affected buildings below, to allow for fire/HVAC interface testing.

Affected areas

When

  • Start: Tuesday 16 May 2023
  • Finish: Tuesday 16 May 2023
  • Times: 6:00am to 12:00pm

Work details

  • The design of the air conditioning system is to shut down during a fire alarm.
  • Test time should be off no longer than one hour.
  • The impacts from these tests will be minimal, and any changes to the environment should be mild.

Contact

Dale Coulson, Service Technical:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

Return to Road and Building works