Facade Replacement Works: UQ Centre (27A) Fortnightly Lookahead

15 Jun 2023

The UQ Centre (27A) cladding replacement works are underway. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from March 2023 until May 2024.

Timeframe: 19 June 2023 to 3 July 2023

Affected Area & Disruption

Time

Date

Western Elevation 

  • Cladding removal underway, noisy works expected.
  • Access through Union Rd will remain open.
  • EWP use to Southwest upper section, Structural works to commence. The toilets will be closed whilst working in this area; Elevator will still be operational and noisy works are expected.

  • Site Fence along Union Road to remain in place for duration of project.

6:30am – 5:00pm

For Duration of Project

19 June 2023 –
3 July 2023

     Until May 2024

Eastern Elevation

  • Cladding removal underway, noisy works expected.
  • Upper walkway will be closed (accessible in an emergency)
  • Lower walkway will be closed due to Upper-level scaffold build. alternative pedestrian route is located east and adjacent to existing walkways (Refer to Figure 2)

6:30am – 5:00pm

19 June 2023 –
3 July 2023

Northern Elevation

  • Scaffolds Build Underway to northern elevation, starting over emergency exit (opened in emergency) Noisy works expected.
  • Road Closure to entry/exit to hockey carpark. Traffic Management and alternative routes in place. Traffic Management and alternative routes in place.
  • Road Closure to entry to UQ Centre carpark. Traffic Management and alternative routes in place. (Refer to Figure 2)

6:30am – 5:00pm

19 June 2023 –
3 July 2023

Southern Elevation

  1. Cladding removal underway, noisy works expected.
  2. Access to Southeast corner will require EWP, Service Carpark to remain closed.
  3. Pedestrian bridge will be closed during EWP use. Alternative Pedestrian Route will be in place.

 6:30am – 5:00pm

19 June 2023 –
3 July 2023

Figure 2 UQ Centre impacts

North impacts

West impacts

South impacts

Project details

UQ Centre (27A), St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Project Manager:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.