Please be advised there will be plumbing works to the DHW in AEB Level 7 Plant Room.
This work is scheduled to allow for the installation of the new Domestic Hot Water Pumps, where minor noises may occur for the building intermittently (until completion).

Affected areas

  • AEB (49) hot water may be affected as temperature control is calibrated
  • AEB (49) DHW may be affected as temperature control is calibrated

When

  • Start: Tuesday, 27 June 2023
  • Finish: Friday, 30 June 2023
  • Times: 6:00am to 10:00am

Work details

Commissioning for the new pumps will likely cause intermittent disturbances on heating and domestic hot water for the field.
Any noise/vibration disturbances and minor shutdowns will be restricted to unoccupied hours.

Contact

Marcus Daldy, Principal Projects Engineer, Energy

We apologise for the inconvenience this may cause and thank you for your understanding during this time.