The Hawken Engineering Building (50) cladding replacement works have commenced. The notification below provides a fortnightly lookahead for upcoming works.

Timeframe: 17 July 2023 to 31 July 2023

Affected Area & Disruption

Time

Date

  • Contractor removing cladding to North and South of Building, EWPs will be used in areas where cladding is to be removed; please refer to Figure 1 below marked “stage 1” for cladding locations.
  • Some Disconnection of services may be required.
  • Hawken Laneway to be closed during EWP operations.
  • Internal access to areas may be required during removal and installations so some disruption will occur.
  • Noisy works are expected.

Footpath may have intermittent closures, alternative pedestrians’ routes to be put in place.

Bicycle stands located North side of Hawken will be closed and inaccessible.

Motorcycle Parking East of Hawken will be closed and inaccessible.

6:30am – 05:00pm

17 July 2023 to
31 July 2023

Figure 1

Work details

These works form part of the Façade Replacement Program and more information about this program can be found here.

Project details

St Lucia (East Package) cladding replacement project.