Facade Replacement Works: PACE (870) fortnightly lookahead

30 Aug 2023

Some disruption to the Pharmacy Australia Centre for Excellence (870) for the Façade Replacement Project will continue as the contractor progresses with the replacement of the non-compliant combustible cladding scope of work.  These works will cause some intermittent noise and there will be some exclusion zones to footpaths, roads and work zones during these works, managed by the Contractor.

The cladding replacement on the PACE Building is expected to be complete by January 2024. Ongoing communications will be provided to give regular updates regarding upcoming works.

Affected Areas

Duration & Time

Site Operations / Site Establishment

  • Cyclist and pedestrian access is open and managed by traffic control for any closures or disruptions

Ongoing

Level 6 Glazing

  • Outdoor seating area remains closed.
  • Gantry structure to maintain access into lounge area.
  • Steel & Subframe installation – high levels of noise during 5-8AM window. Outside of this time – moderate, intermittent levels of noise for remainder of day.

28 August – 15 September

  • Level 6 balcony remains closed to staff, students and public until further notice.
  • Steel & Subframe installation above L6 balcony continues – Steel & Subframe installation – high levels of noise during 5-8AM window. Outside of this time – moderate, intermittent levels of noise for remainder of day.

28 August – 15 September

Cornwall Street Main Entrance

  • Cladding removal works to commence – moderate levels of noise during removal

28 August to 1 September

  • Cladding Installation – moderate levels of noise during installation

30 August to 15 September

Cornwall Street SW Blade Fin

     Complete – no further disruption expected for remainder of project.

                      N/A

Lecture Theatre

Complete – no further disruption expected for remainder of project.

                      N/A

Please refer attached plans for affected areas (PDF, 1.8 MB) and lookahead (PDF, 446.5 KB).

Project details

Cladding replacement on the PACE Building which forms part of the wider UQ Façade Replacement Program.

Contact

Casey Fredrickson, Senior Project Manager (Infrastructure):

We apologise for the inconvenience this may cause and thank you for your understanding during this time.