Facade Replacement Works: UQ Centre (27A) fortnightly lookahead

28 Aug 2023

The UQ Centre (27A) cladding replacement works are underway. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from March 2023 until May 2024.

Timeframe: 28 August 2023 to 11 September 2023

Affected Area & Disruption

Time

Date

Western Elevation 

  1. Cladding removal and installation continuing where access is in place, noisy works expected.
  • Union Road entry will be partially reduced for scaffold erection above on the nominated dates. (Refer to West Impacts Image below)
  • Site Fence along Union Road to be in place for duration of project. Road will remain open.

6:30am – 5:00pm

6:30am – 5:00pm

For Duration of Project

28 August 2023 – 11 September 2023

30 August 2023 – 13 September 2023

Until May 2024

Eastern Elevation

  • Cladding removal and installation continuing, noisy works expected.
  • EWPs will be in use and this machinery creates a beeping noise.
  • Walkway will be closed during operations and crane lifts. Alternative pedestrian routes will be in place. (Refer to East Impacts Image below)

6:30am – 5:00pm

28 August 2023 to 11 September 2023

Northern Elevation

  • Cladding removal and installation continuing, noisy works expected.
  • Material deliveries to the hoist – intermittent impacts to roadways / car parks.

6:30am – 5:00pm

28 August 2023 to 11 September 2023

Southern Elevation

  1. Cladding removal and installation continuing, noisy works expected.
  2. EWP will be used to access Southeast corner, Service Carpark on ground level to remain closed. (Refer to South Impacts Image below)
  3. Pathway under Walkway bridge on ground level to be closed. Alternative pedestrian route to be put in place.

6:30am – 5:00pm

28 August 2023 to 11 September 2023

A solar panels on top of a buildingDescription automatically generated

Figure 2 UQ Centre Site Works

Aerial view of a building with solar panelsDescription automatically generated

East Impacts

West Impacts

South Impacts

A collage of a buildingDescription automatically generated

Project details

 

UQ Centre, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.