Please be advised there will be a power shut down at the Gatton Campus in the area north of the highway to allow for electrical upgrade and maintenance works.
Affected areas
- Horticulture Buildings and Greenhouses on John Howe Memorial Drive
- Dwelling No. 26, 27, 28 and 29 on John Howie Memorial Drive
- Sewerage Treatment Plant
- Wind Tunnel and Agricultural Chemical Handling & Storage Facility on John Howie Memorial Drive
- Farms offices adjacent to the Sewerage Treatment Plant (old CSIRO compound)
When
Session 1 – For a period of 1.5 hours
- Start: Monday 21 August 2023
- Finish: Monday 21 August 2023
- Times: 10:00am – 12:00pm (For a period of 1.5hrs)
Session 2 – Whole day shutdown
- Start: Friday 25 August 2023
- Finish: Friday 25August 2023
- Times: 7:00am – 5:00pm (Whole day shut down)
Affected areas The following areas will be affected for a longer period of time | |||
Dwelling No. 29 on John Howie Memorial Drive | Start: 10:00am Monday 21 August 2023 | Finish: 5:00pm Friday 25 August 2023 | Times: For a period of 5 days, including out of hours |
Building 8414 – Hortifield Polyethylene Covered Growth House | Start: 10:00am Monday 21 August 2023 | Finish: 5:00pm Friday 25 August 2023 | Times: For a period of 5 days, including out of hours |
Hortifield Lysimetry Greenhouse | Start: 10:00am Monday 21 August 2023 | Finish: 5:00pm Friday 25 August 2023 | For a period of 5 days, including out of hours |
Work details
These shutdowns are required for the overhead HV replacement and realignment works which are currently underway.
Contact
Casey Fredrickson, Project Manager:
- Call: +61 408 339 936
- Email: c.fredrickson@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.